Map approval time and fees by authority: LDA, RDA, CDA, SBCA and more
Updated
How long a house map (building plan) approval takes, authority by authority, from two kinds of source kept apart: the time the authority's own regulation, procedure or service page gives, quoted with its date, and dated news reports of actual times, labelled as reports. Plus what you can do online, and a calculator for the building plan fee from each authority's own fee schedule.
We read every source on 18 November 2026. Where an authority's own text gives no time, its section says so; we don't fill the gap with a report.
Map approval fee calculator
Pick the authority, the use and your plan's covered area. Where the authority's own schedule prints a fee per sq ft, we multiply it out; where it prints none we could read, the line says to ask, with no number.
Fee estimate
Enter the covered area to see the fee.
Building plan (scrutiny) fee Rs 6 × 2,000 sq ft
Rs 12,000
Completion certificate fee, paid when the house is complete The schedule charges the same as the approval fee
Rs 12,000
Anything else the authority puts on your challan No schedule we read lists every charge. Ask the authority for its full challan.
Ask
Total of the lines with a figure
Rs 24,000
Plus 1 line to ask the authority about
Estimate from CDA's schedule dated 16 August 2023, not a challan.
One row per authority: its own figure, the newest dated report we found, and its online service. The quotes and links are in each authority's section below.
“The total processing time for building plan approval is 32 working days, subject to the submission of all required documents, drawings, and fees, and provided there are no observations or objections”
The same FAQ also answers "How much time it will take to sanction the building plan?" with: "It will take 30 days for final approval of building plan." The two answers differ, and we give both. eBiz Punjab is the Punjab government portal LDA's home page links for "Building Plan Approval", and its FAQ says LDA "ensures that building plans comply with zoning regulations, safety norms, and development bylaws". To find it, search "Building Construction" on eBiz Punjab, choose Residential, go on to Required Documents and open the FAQs tab. LDA's own FAQ and application requirements pages give no time.
What news reports say
Report, ProPakistani, citing sources, 7 May 2026: “pending requests at the LDA’s One Window Cell are now taking up to 18 days” Read the report
Online
eBiz Punjab LDA's home page links "Building Plan Approval" to the Punjab government's eBiz portal, where "Building Construction" opens an application form. LDA's home page also has a One Window application status tracker.
The checklist prints this as a graphic beside its residential plan scrutiny fee, and carries no date. It gives no time for apartment or commercial plans.
What news reports say
We found no dated news report of actual approval times for this authority in 2025 or 2026.
Online
RDA Digital Services offers a sign-in and public checks of a society's or a plot's status, but doesn't say plans can be submitted there.
The same SOP gives 15 days for private housing schemes and the MDA-controlled area, for M.I.T. housing schemes and for LMQ Road, Vehari Road and Bosan Road, and 10 days for clearance by the Building Plan Scrutiny Committee. The SOP prints no date.
What news reports say
We found no dated news report of actual approval times for this authority in 2025 or 2026.
Online
MDA's online application portal lists possession, transfer, NOC and other services, but not building plan approval.
Fees
Building plan fee for residential plots: Rs 14.00 per sq ft, the 2025-26 figure, because the 2026-27 figure on the same sheet is not clearly legible on MDA's scan. The sheet raises its fees by 10% for 2026-27.
The clause covers plans submitted through an architect in line with the regulations: within that period CDA tells the owner and the architect whether the plan is approved, or its reasons in writing. Before the 2023 amendment the same clause said 21 days.
What news reports say
Report, Dawn, 11 April 2026: “after the passage of two and a half years, the board’s decision has not yet been implemented” Read the report
Report, Dawn, on a CDA press release, 5 December 2023: “Residential buildings of 356 yards will now be approved with an additional fee of Rs20,000 with required documents within two days” Read the report
Online
We found no CDA page for submitting a house plan online on 18 November 2026. CDA's FAQ lists the forms and copies to hand in.
Fees
Residential: Rs 6 per sq ft of covered area, or Rs 10,000 if that is higher
Commercial: Rs 20 per sq ft of covered area, or Rs 30,000 if that is higher
The completion certificate costs the same fee again.
The 15 days count from when the objections are met, not from submission. For one of SBCA's pre-approved designs, the same sheet says approval shall be issued within 5 days.
What news reports say
Report, ARY News, on the Auditor General's audit for 2024-25, 31 October 2026: “the time required to approve building plans had increased more than fourfold compared with 2019” Read the report
Report, Nukta, 7 July 2025: “Applicants face delays of up to 457 days” Read the report
Online
SBCA Single Window Facility Plans are submitted online by a licensed professional. SBCA's own count: 18,256 proposals from 1 November 2019 to 18 November 2026, and 17,575 construction permits issued.
Fees
Residential: Rs 16.5 per sq ft of covered area, in FBR valuation categories I, A-I, II, III, IX or X
Residential: Rs 12 per sq ft of covered area, in FBR valuation categories IV, V, VI, VII or VIII
Commercial: Rs 22 per sq ft of covered area, in FBR valuation categories I, A-I, II, III, IX or X
Commercial: Rs 17.5 per sq ft of covered area, in FBR valuation categories IV, V, VI, VII or VIII
The same page names the Assistant Municipal Officer as the officer responsible and the Chief Municipal Officer for appeals. It gives 30 days for a commercial plan outside the walled city of Peshawar and 15 days inside it.
What news reports say
We found no dated news report of actual approval times for this authority in 2025 or 2026.
Ask the authority: we found no fee schedule it publishes for house plans.
Other authorities
Peshawar Development Authority's website did not load for us on 18 November 2026, and Punjab's Local Government department says a plan is processed under the building bye-laws of the local government concerned, without giving a time. Elsewhere, ask your development authority or municipal body for its time limit.
How to read these times
An authority's time is what its own regulation, SOP or service page says. It may count working days, and from a complete file or from when objections are met, so read the note under each quote.
A news report is what an outlet published on its date, often from unnamed sources, an inspection or an audit. We quote it; we have not checked it against the authority's records.
Where we found no time in the authority's own text, we say so instead of using a report.
Times and fees change. Before you apply, ask the authority for its current time limit and fee in writing.
eBiz Punjab, the portal LDA's home page links for building plan approval, says in the FAQ of its Building Construction application that "the total processing time for building plan approval is 32 working days", when all documents, drawings and fees are in and there are no observations or objections. Another answer in the same FAQ says "It will take 30 days for final approval of building plan." We read both on 18 November 2026. ProPakistani reported on 7 May 2026, citing sources, that pending requests at LDA's One Window Cell were "taking up to 18 days".
How long does CDA take to approve a house map?
CDA's Building Control Regulations, as amended in August 2023, say CDA shall tell the owner and the architect whether a plan is approved, or why not, within 10 working days of submission, for plans submitted through an architect in line with the regulations.
How long does SBCA map approval take in Karachi?
SBCA's procedure says approval is issued within 15 days after objections are met, or within 5 days for one of its pre-approved designs. Nukta reported on 7 July 2025 "delays of up to 457 days", and ARY News reported on 31 October 2026 that an audit found the time had grown more than fourfold since 2019.
Can I apply for map approval online?
In Karachi, through SBCA's Single Window Facility, by a licensed professional. LDA's website sends building plan approval to eBiz Punjab, and KP's local governments have the LGKP Online Building Map Approval portal. We found no online plan submission for CDA, RDA or MDA on 18 November 2026.
What is the map approval fee?
It is charged per sq ft of covered area, at the authority's own rate. CDA's Building Control Regulations (amended August 2023) charge Rs 6 per sq ft for a residential building, or Rs 10,000 if that is higher, and the same again for the completion certificate. SBCA's January 2023 notification charges Rs 16.50 or Rs 12.00 per sq ft for a residential plan in Karachi, by the area's FBR valuation category. LDA's Building and Zoning Regulations 2019 charge Rs 15 per sq ft of covered area for a residential plan and Rs 40 for a commercial one. RDA's checklist for residential plans gives Rs 10 per sq ft. GDA's FAQ page gives Rs 15 per sq ft for a commercial plan. For FDA, MDA's current year and the local governments, we found no current figure we could read, so ask the authority. The calculator above works out the figure for your covered area.
Map pass hone mein kitne din lagte hain?
Har authority ka apna waqt hai: CDA 10 working days, SBCA objections poore hone ke baad 15 din (pre-approved design par 5 din), MDA ki apni scheme mein 7 din, aur KP ki TMA 10 din. LDA ke liye eBiz Punjab ke FAQ mein 32 working days likhe hain (wahin ek aur jawab 30 din kehta hai). RDA ka waqt hamein us ki apni website par nahi mila. Har authority ka source aur tareekh upar di gayi hai.