500 sq yd house construction cost in Karachi
What it costs to build a 500 sq yd house in Karachi at contractor rates as of Sep 2026, as grey structure and complete, for the house described below. Change anything in the calculator to match your plans.
The house these figures assume
| Plot | 500 sq yd (4,500 sq ft) |
|---|---|
| Storeys | 2 (an assumption) |
| Ground coverage | 75% |
| Covered area | 6,750 sq ft, the footprint on every storey |
An assumption. We could not get SBCA's own copy of the Karachi Building and Town Planning Regulations 2002 to cite its coverage table, so check your plot's figure with SBCA or your architect.
The storeys and coverage are inputs: change them in the calculator below.
Cost by finish level
Each row is a contractor rate band for Karachi: its range per sq ft of covered area, what it comes to for this house, its date and its sources.
Rates are contractor-quoted ranges per sq ft of covered area, materials and labour included. What "grey structure" and "complete" include varies by contractor, so compare quotes line by line.
Change the numbers
Estimated cost
Enter a plot size, a coverage between 1% and 100% and a rate above zero.
Rs
Range Rs 4.05 crore to 5.43 crore
- Covered area
- 6,750 sq ft
- Rate used
- Rs 6,000 to 8,050 per sq ft
- Basement (grey works)
- Midpoint
- Rs 47,418,750
Patwari's estimate from contractor rates. It excludes the plot, approvals and utility connections. Get written quotes before you build.
Rates are contractor-quoted ranges per sq ft of covered area, materials and labour included. What "grey structure" and "complete" include varies by contractor, so compare quotes line by line.
Material prices this week: Karachi
The latest official prices for the main materials and wages. They don't change the estimate above. Use them to check a contractor's quote.
| Item | Price (Rs) | As of | Source |
|---|---|---|---|
| Cement, per 50 kg bag | 1,481 | 29 Oct 2026 | PBS weekly SPI |
| Mason, per day | 2,491 | 29 Oct 2026 | PBS weekly SPI |
| Labourer, per day | 1,478 | 29 Oct 2026 | PBS weekly SPI |
| Bricks, per 1,000 (new first class) | 22,000 | Oct 2026 | PBS monthly construction prices |
| Crush (bajri), per truck (100 cft) | 9,253 | Oct 2026 | PBS monthly construction prices |
| Sand, per truck (100 cft) | 8,233 | Oct 2026 | PBS monthly construction prices |
| Iron bars, per tonne (1/2 inch, 40 grade) | 239,450 | Oct 2026 | PBS monthly construction prices |
| Plumber, per day | 2,405 | Oct 2026 | PBS monthly construction prices |
| Electrician, per point | 418 | Oct 2026 | PBS monthly construction prices |
Prices from Pakistan Bureau of Statistics data. Figures we derive from them are Patwari's estimates, not official PBS statistics.
Questions about building a 500 sq yd house in Karachi
How much does it cost to build a 500 sq yd house in Karachi?
About Rs 4.74 crore for a complete house at the standard finish level (Rs 4.05 crore to 5.43 crore), at Karachi contractor rates as of 10 Jul 2026. That is 6,750 sq ft of covered area: 2 storeys at 75% ground coverage. From the lowest to the highest finish level we have a rate for, the range is Rs 4.04 crore to 6.41 crore.
What is the construction cost per sq ft in Karachi?
Contractors in Karachi quote Rs 2,850 to 3,500 per sq ft of covered area for grey structure and Rs 5,980 to 9,500 for a complete house, depending on the finish level, with materials and labour included (rates as of Sep 2026).
How much does grey structure cost for a 500 sq yd house in Karachi?
About Rs 2.01 crore at the standard finish level (Rs 1.92 crore to 2.09 crore), at Rs 2,850 to 3,100 per sq ft for 6,750 sq ft of covered area (rates as of Sep 2026).
What does grey structure include?
Grey structure is the frame, walls, roof and plaster, without finishing. What it includes varies by contractor, so compare quotes line by line.
How much does finishing cost for a 500 sq yd house in Karachi?
About Rs 2.73 crore at the standard finish level: the difference between the complete and grey structure midpoints (Rs 4.74 crore and Rs 2.01 crore) for 6,750 sq ft (rates as of Sep 2026). Finishing covers flooring, wiring, plumbing, doors, paint and fittings.